ITEM 17. A Resolution approving Change Order No. 1 to the contract with Bulls Construction Group LLC, P.O. Box 360302, Birmingham, in the amount $68,626.87, for the Greensprings Highway Streetscape Phase I, with the adjusted contract price increasing to a

under review Public Works
$68,626 , Yellow tier ($50,000 to $250,000)

We couldn't match a specific vote to this item in the minutes. View full minutes ↗