docket.pub
Public meeting intelligence
⌕
/
/al/ birmingham/ overview
Policy badge · Birmingham

Public-Safety Tech & Privacy

Council decisions on police technology, surveillance, and data-sharing arrangements that affect resident privacy.

Volume timeline

Public-Safety Tech & Privacy — items per month

Indexed so far 15772 items in last 171 months
Total dollars $1718.6M where disclosed
Notice: Hatched months are still being indexed (64.6% of agenda items processed so far).
20 10 0 2022-01-01: 154 items, $2.7M 2022-02-01: 105 items, $867,383 2022-03-01: 125 items, $276,273 2022-04-01: 111 items, $2.1M 2022-05-01: 194 items, $8.9M 2022-06-01: 165 items, $10.0M 2022-07-01: 107 items, $5.1M 2022-08-01: 104 items, $10.5M 2022-09-01: 135 items, $438,084 2022-10-01: 103 items, $1.7M 2022-11-01: 111 items, $2.9M 2022-12-01: 33 items, $4.7M 2023-01-01: 102 items, $16.2M 2023-02-01: 136 items, $9.5M 2023-03-01: 78 items, $1.4M 2023-04-01: 167 items, $7.2M 2023-05-01: not indexed yet 2023-06-01: not indexed yet 2023-07-01: not indexed yet 2023-08-01: not indexed yet 2023-09-01: not indexed yet 2023-10-01: not indexed yet 2023-11-01: not indexed yet 2023-12-01: not indexed yet 2024-01-01: 92 items, $3.5M 2024-02-01: 101 items, $673,345 2024-03-01: 63 items, $307,629 2024-04-01: 32 items, $569,582 2024-05-01: 101 items, $8.0M 2024-06-01: 82 items, $2.4M 2024-07-01: 118 items, $4.6M 2024-08-01: 91 items, $557,939 2024-09-01: 145 items, $7.7M 2024-10-01: 138 items, $2.4M 2024-11-01: 41 items, $10.0M 2024-12-01: 180 items, $10.8M 2025-01-01: 102 items, $7.9M 2025-02-01: 99 items, $6.9M 2025-03-01: 99 items, $5.2M 2025-04-01: 160 items, $1.2M 2025-05-01: 96 items, $4.5M 2025-06-01: 101 items, $13.1M 2025-07-01: 180 items, $18.6M 2025-08-01: 181 items, $9.4M 2025-09-01: 169 items, $2.0M 2025-10-01: 187 items, $2.3M 2025-11-01: 85 items, $2.5M 2025-12-01: 153 items, $3.2M 2026-01-01: 129 items, $5.0M 2026-02-01: 55 items, $1.9M 2026-03-01: 202 items, $5.0M 2026-04-01: 93 items, $865,995 2026-05-01: 119 items, $2.4M 2026-06-01: not indexed yet 2026-07-01: not indexed yet 2026-08-01: not indexed yet 2026-09-01: not indexed yet 2026-10-01: not indexed yet 2026-11-01: not indexed yet 2026-12-01: not indexed yet 2022 2023 2024 2025 2026
Filters
Items

25 items of many

June 9, 2020 · Item number:Item #10 · 🛡️ Public-Safety Tech & Privacy Total cost: undisclosed

Nuisance abatement: City to clear blighted properties, assess costs as liens

City will remove overgrown vegetation and debris from neglected properties and charge owners for cleanup costs. Costs become liens on properties if unpaid.

Funding source: Unknown Action type: Weed abatement
June 9, 2020 · Item number:Item #67 · 🛡️ Public-Safety Tech & Privacy Total cost: undisclosed

City adopts management control agreement with emergency communications district

Establishes formal oversight of Birmingham's 911 dispatch and emergency response system, required by federal criminal justice authorities to ensure accountability and efficient emergency services.

Counterparty: Birmingham Emergency Communications District (BECD) Funding source: Unknown Action type: Ordinance
June 2, 2020 · Item number:Item #97 · 🛡️ Public-Safety Tech & Privacy Total cost: $130K

Fire Station 13 reroofing awarded to Johns and Kirksey Inc. for $129,500

City commits $129,500 to repair Fire Station 13's roof and soffit, keeping the facility safe and functional for emergency response.

Counterparty: Johns and Kirksey, Inc. Funding source: General Fund Action type: Contract award Location: Birmingham Fire Station 13
June 2, 2020 · Item number:Item #119 · 🛡️ Public-Safety Tech & Privacy Total cost: $50K

Sole-source contract: City pays GSBC Community Development $50K

City commits $50,000 to GSBC Community Development Corporation for goods and services. Contract bypasses competitive bidding as a sole-source purchase.

Counterparty: GSBC Community Development Corporation Funding source: Unknown Action type: Contract award
June 2, 2020 · Item number:Item #86 · 🛡️ Public-Safety Tech & Privacy Total cost: $13K

Property owner billed $12,818 for emergency demolition on Bankhead Highway

City demolished an unsafe building and is recovering the $12,818 cost through a special assessment against the property owner. Property owners at 1201 Bankhead Highway will receive this bill.

Funding source: Special Tax Action type: Demolition Location: 1201 Bankhead Highway, Birmingham
June 2, 2020 · Item number:Item #69 · 🛡️ Public-Safety Tech & Privacy Total cost: $10K

Special assessment: $10,230 for demolition at 8224 Division Ave

Property owner at 8224 Division Avenue will be charged $10,230.37 to cover the city's cost for demolishing an unsafe building on their lot.

Funding source: Special Tax Action type: Demolition Location: 8224 Division Avenue, Birmingham
June 2, 2020 · Item number:Item #72 · 🛡️ Public-Safety Tech & Privacy Total cost: $9K

Special assessment: $9,498 demolition cost at 6610 1st Ave S

Property owner at 6610 1st Avenue South will be billed $9,498.24 to cover the city's cost of tearing down an unsafe building on the site. The amount becomes a lien against the property.

Funding source: Special Tax Action type: Demolition Location: 6610 - 1st Avenue South, Birmingham
June 2, 2020 · Item number:Item #80 · 🛡️ Public-Safety Tech & Privacy Total cost: $9K

City assesses $9,079 demolition cost to 7612 5th Ave South

Property owner will be billed for the city's emergency demolition of an unsafe building. Special assessment charges are added to the property's tax bill.

Funding source: General Fund Action type: Demolition Location: 7612 - 5th Avenue South, Birmingham
June 2, 2020 · Item number:Item #63 · 🛡️ Public-Safety Tech & Privacy Total cost: $8K

Demolition cost assessment: $8,435 charged to 8509 Cedarbark Circle

Property owner will receive a bill for the city's demolition of an unsafe building on their lot. This becomes a lien on the property until paid.

Funding source: General Fund Action type: Demolition Location: 8509 Cedarbark Circle, Birmingham
June 2, 2020 · Item number:Item #64 · 🛡️ Public-Safety Tech & Privacy Total cost: $8K

Demolition cost assessment: $8,435 charged to 8509 Cedarbark Circle

Property owner will receive a bill for the city's demolition of an unsafe building on their lot. This becomes a lien on the property until paid.

Funding source: General Fund Action type: Demolition Location: 8509 Cedarbark Circle, Birmingham
June 2, 2020 · Item number:Item #75 · 🛡️ Public-Safety Tech & Privacy Total cost: $8K

City charges property owner $8,412 for unsafe building demolition

Property owner at 7009 1st Avenue South must pay the city's demolition costs for an unsafe structure. Special assessments like this recover public spending on blighted properties directly from owners.

Funding source: General Fund Action type: Demolition Location: 7009 - 1st Avenue South, Birmingham
June 2, 2020 · Item number:Item #70 · 🛡️ Public-Safety Tech & Privacy Total cost: $8K

City charges property owner $7,791 for demolition of unsafe building at 6709 1st

Property owner at 6709 1st Avenue South now owes the city $7,791 to cover demolition costs for an unsafe structure. This special assessment lien can affect the property's title and future sale or refinancing.

Funding source: Special Tax Action type: Demolition Location: 6709 - 1st Avenue South, Birmingham
June 2, 2020 · Item number:Item #87 · 🛡️ Public-Safety Tech & Privacy Total cost: $7K

Special assessment: $7,284 demolition cost at 3233 28th Avenue North

Property owner receives bill for emergency demolition of unsafe building. Assessment is placed against the property and must be paid or added to tax debt.

Funding source: Unknown Action type: Demolition Location: 3233 - 28th Avenue North, Birmingham
June 2, 2020 · Item number:Item #67 · 🛡️ Public-Safety Tech & Privacy Total cost: $7K

City bills owner $7,222 for demolition of unsafe building at 3rd Ave South

Property owner at 8015 3rd Avenue South must pay $7,222 to cover the city's cost to tear down an unsafe structure. This is a final bill for work already completed.

Funding source: Unknown Action type: Demolition Location: 8015 - 3rd Avenue South, Birmingham
June 2, 2020 · Item number:Item #66 · 🛡️ Public-Safety Tech & Privacy Total cost: $7K

City bills owner $7,222 for demolition of unsafe building at 3rd Ave South

Property owner at 8015 3rd Avenue South must pay $7,222 to cover the city's cost to tear down an unsafe structure. This is a final bill for work already completed.

Funding source: Unknown Action type: Demolition Location: 8015 - 3rd Avenue South, Birmingham
June 2, 2020 · Item number:Item #79 · 🛡️ Public-Safety Tech & Privacy Total cost: $6K

Special assessment: $6,284.92 for demolition at 7130 Division Avenue

Property owner at 7130 Division Avenue will be billed $6,284.92 to cover the city's cost of demolishing an unsafe building on the site. This assessment becomes a lien against the property.

Funding source: Special Tax Action type: Demolition Location: 7130 Division Avenue, Birmingham
June 2, 2020 · Item number:Item #76 · 🛡️ Public-Safety Tech & Privacy Total cost: $6K

City charges property owner $6,152 for unsafe building demolition

Property owners at 7300 2nd Avenue South now owe the city $6,152 for demolition of an unsafe structure. The cost will be collected as a special assessment against the property.

Funding source: Special Tax Action type: Demolition Location: 7300 - 2nd Avenue South, Birmingham
June 2, 2020 · Item number:Item #109 · 🛡️ Public-Safety Tech & Privacy Total cost: $6K

City pays Wittichen Supply $5,626 for South Precinct HVAC repair

Police South Precinct gets working air conditioning restored. Necessary facility maintenance to keep precinct operational.

Counterparty: Wittichen Supply Co., Birmingham Funding source: General Fund Action type: Contract award Location: Birmingham Police South Precinct
June 2, 2020 · Item number:Item #74 · 🛡️ Public-Safety Tech & Privacy Total cost: $5K

City charges property owner $5,406 for unsafe building demolition

Demolition cost for the condemned building at 6817 1st Avenue South is being passed to the property owner as a special assessment. This recouples the expense with the responsible party rather than spreading it across taxpayers.

Funding source: Unknown Action type: Demolition Location: 6817 - 1st Avenue South, Birmingham
June 2, 2020 · Item number:Item #73 · 🛡️ Public-Safety Tech & Privacy Total cost: $5K

Special assessment: $5,191 demo cost for 6716 Division Ave

Property owner at 6716 Division Avenue will be billed $5,191 to cover the cost of demolishing an unsafe building. The charge becomes a lien on the property.

Funding source: Special Tax Action type: Demolition Location: 6716 Division Avenue, Birmingham
June 2, 2020 · Item number:Item #90 · 🛡️ Public-Safety Tech & Privacy Total cost: $5K

City recovers $4,846 demolition cost from property owner at 1014 Cahaba

Property owner faces special assessment to repay the city for emergency demolition of an unsafe building. Removes blighted structure from neighborhood.

Funding source: Unknown Action type: Demolition Location: 1014 Cahaba Street, Birmingham
June 2, 2020 · Item number:Item #92 · 🛡️ Public-Safety Tech & Privacy Total cost: $5K

Emergency demolition cost billed to owner: 200-60th St North ($4,757)

Property owner at 200-60th Street North faces a $4,757 bill for the city's emergency demolition of an unsafe building. The cost becomes a legal assessment against the property.

Funding source: Unknown Action type: Demolition Location: 200 - 60th Street North, Birmingham
June 2, 2020 · Item number:Item #62 · 🛡️ Public-Safety Tech & Privacy Total cost: $5K

Property owner charged $4,618 for unsafe building demolition at 5008 Jefferson A

The owner of 5008 Jefferson Avenue S.W. must pay the city's demolition costs for an unsafe structure. This assessment becomes a lien on the property until paid.

Funding source: General Fund Action type: Demolition Location: 5008 Jefferson Avenue S.W., Birmingham
June 2, 2020 · Item number:Item #84 · 🛡️ Public-Safety Tech & Privacy Total cost: $5K

Emergency demolition: Property owner billed $4,614 for 1009 19th Street S.W.

City demolished an unsafe building and is charging the property owner $4,614 to recover the cost. The property owner is now liable for the emergency removal.

Funding source: Unknown Action type: Demolition Location: 1009 - 19th Street S.W., Birmingham
June 2, 2020 · Item number:Item #81 · 🛡️ Public-Safety Tech & Privacy Total cost: $5K

Property owner billed $4,551.60 for emergency demolition at 1000 - 19th Street S

City paid to tear down an unsafe building; property owner now gets a special tax bill to repay demolition costs. This charge becomes a lien on the property.

Counterparty: property owner at 1000 - 19th Street S.W. Funding source: Special Tax Action type: Demolition Location: 1000 - 19th Street S.W., Birmingham
Menu
More