· Item number:Item #2025-13 $ Total cost: $79K Change order adds $79,493 to N. McGregor Ave. project John G. Walton Construction gets additional $79,493 to complete 2018 street improvements on N. McGregor Ave., raising the total contract value.
· Item number:Item #2025-3 $ Total cost: $161K City and Park Building, LLC share $160,888 for Wet Willis sidewalks City commits $160,888 to improve sidewalks in the Wet Willis neighborhood. Cost-sharing agreement splits the project expense with Park Building, LLC.
· Item number:Item #2025-9 $ Total cost: $245K City awards $245K contract to TTL, Inc. for Eslava Creek work TTL, Inc. will manage capital improvements on Eslava Creek between Lleyn and Montlimar Avenues—part of the city's planned infrastructure upgrades in that corridor.