$540.7K change order for Intermodal Facility Phase 2 construction

Contracts & Procurement
$540,656 , Orange tier ($250,000 to $1 million)

Adds $540,656 to the Rabren General Contractors contract for Phase 2 general trades work. Change orders reflect scope adjustments; this funds additional labor, materials, or scheduling changes needed to complete the facility's second phase.

Counterparty: Rabren General Contractors, Auburn, Alabama Funding source: Unknown Action type: Contract amendment

We couldn't match a specific vote to this item in the minutes. View full minutes ↗